11 June 2022 – Due to the adverse weather conditions of the last days, the schedule of the sea campaign had to be redefined.
Here is the updated plan:
- the ship left Malta this afternoon, to be back at the ARCA site tonight
- the deep sea activities will be started already during the night
- DU deployments will be started tomorrow
- end of the operation is foreseen for early next week
Good luck to our offshore and onshore teams!